Enhancements to the interior and exterior are coming to the St. Clair Beach Community Centre starting in July 2026. These improvements will ensure the centre meets the diverse needs of the community by extending the offerings of the facility, improving accessibility, and enhancing its overall appeal. The project is set to be completed by February 2027.

The St. Clair Beach Community Centre is a 4000 square foot facility located at 13731 St. Gregory's Road, Tecumseh, ON.

This renewal project will include these key improvements:

  • New Multi-Use Program Room With an Operable Partition Wall
  • New Men’s, Women’s, and Universal washrooms.
  • New Serveries/Kitchenette
  • New Reception/Common area
  • New Storage Facilities
  • New Enclosed Refuse Area
  • Exterior Window Replacements
  • New Main Entrance Lobby
  • New Exterior Lighting
  • New ACM Paneling on Existing Façade
  • Mechanical and Electrical Upgrade
  • Sanitary System Upgrades
  • Sidewalk Reconstruction

Compare

Swipe to compare current interior and exterior spaces to the proposed 3D design renderings.

Exterior 1

Before After
Before After

Exterior 2

Before After

Interior 1

Before After

Interior 2

Before After

Interior 3

Before After

Construction Schedule

Please note construction schedules are subject to change
  • Timeline item 1 - active

    July 2026

    Start of project construction / Phase 1 Demolition

  • Timeline item 2 - incomplete

    August 2026

    Continuation of Phase 1 Demolition

  • Timeline item 3 - incomplete

    September 2026

    Phase 1 Demolition complete / beginning of Phase 2 Finishing Works

  • Timeline item 4 - incomplete

    October 2026 to January 2027

    Continuation of Phase 2 Finishing Works / Project near completion

  • Timeline item 5 - incomplete

    February 2027

    Project complete followed by a plan to reopen in 2027